The job sounds enormous — “replace every drain in the house” — but it's a sequenced trade routine that experienced crews run week in, week out. Cast Iron Oshawa lays the sequence out below for one reason: a homeowner who knows the steps can read a quote line by line, ask the right questions, and spot the corner being cut when a number looks too good.
The sequence
- Step 1
Scope and written quote
A camera pass maps what's failing and where. The quote that follows itemizes what's being replaced (stack only, or stack plus galvanized branches), what walls open, who restores them, permit scope and the schedule. Vague quotes produce disputed invoices — insist on the itemized version.
- Step 2
Permit and protection
Drain replacement of this scope is permitted plumbing work under the Ontario Building Code, filed with the municipality. On day one the crew sheets off work areas, floors get protected, and furniture near the stack wall moves out of the dust path.
- Step 3
Opening access
The stack lives in a wall chase from basement to roof; branches run through floors and joist bays. Drywall or plaster opens along those routes — the honest quote said exactly where beforehand. In many Oshawa bungalows the basement portion is already exposed, which is what keeps typical jobs near the low end of the cost range.
- Step 4
Cutting out the iron
Water goes off in planned windows. The cast iron comes out top-down in manageable lengths — snapped with a chain cutter or ground through — with every section supported before it's cut, because a hub-and-spigot stack carries real weight. The old metal leaves the house for recycling; disposal should be in the quote, not a surprise.
- Step 5
New pipe in ABS
The new stack, branches and vents go in — solvent-welded ABS on proper hangers and grade, joined to any remaining sound pipe with shielded mechanical couplings. This is also when decades of improvisation get corrected: undersized vents, flat-graded branches, an S-trap someone installed in 1978. The system comes out matching current code, not a copy of the 1960 original.
- Step 6
Test and inspection
The new drains are tested — plugged and filled, or air-tested — and the municipal inspector signs off before walls close. That inspection record matters beyond the day itself: it's the document a future buyer's agent, home inspector or insurer accepts as proof the work was done right.
- Step 7
Closing up
Insulation reinstated where exterior walls were opened, drywall, tape and finish. Quotes handle restoration differently — included, subcontracted or explicitly excluded (“drywall by others”) — and the only wrong version is the one you didn't notice until the crew left. Then water back on, and the house drains like it's 2026 instead of 1962.
Living through it
Typical stack replacements run on the order of a few days; full-house re-pipes with branch replacement and restoration run longer. Water is off only in planned windows, announced ahead — most families stay home throughout. The noisy, dusty day is the demolition-and-cut-out day; from Step 5 on it's ordinary quiet plumbing work. If the buried under-slab run is being replaced in the same project, add slab-breaking days and see the sewer line page for that half of the story.